Apache Energy – Ocean Legend Platform DCS/SIS Replacement

Hero Engineering completes Apache Energy Ocean Legend manned platform DCS/SIS replacement. The 2500 physical I/O Siemens PCS7 DCS replaced the original APACS DCS.  The new system comprises Siemens Process Device Manager  (PDM), DBA Tools, Solar Turbines’ unit control integration, bussed MCCs, fluenta flare gas and CALM Buoy serial packages.  The project was completed in 8 months without any platform […]

AnaeCo Bioconversion Plant Stage 2

Hero Engineering awarded electrical, instrumentation, control and safety system detailed design and coding for Stage 2 of the AnaeCo DiCOM AWT Facility in Shenton Park. Stage 2 is the commercialisation of the 55,000 tpa DiCOM process that will provide Energy, recycled material and compost to the Perth market. The plant automation comprises gas analysers and over 150 drives controlled […]

Tiwest IPS and SCADA works

Hero Engineering to undertake Safety Systems modifications, SIL validation and commissioning of a Moore Quadlog safety systems.  The project will use the HeroSafe Safety Management System in full compliance to IEC61508/IEC61511 to manage all changes and close-out activities.

Office Purchase for Hero Engineering

Hero Engineering purchases 500sqm office in Belmont. The building fit-out incorporates modern offices, workshop and training facilities and uses the latest IT infrastructure and security. [singlepic id=47 w=400 float=none]

HeroSafe – Functional Safety Management System

With the increased requirement of operating companies and functional safety service providers to comply with IEC61508, Hero Engineering has developed the HeroSafe Functional Safety Management System (FSM).  HeroSafe covers the functional safety life cycle as documented in IEC61508/61511. The system has been compiled with input from all Hero Engineering FSEngs that have wide industry experience […]